Dismantling of the main ring magnet power supply for proton accelerators

  • 1. High Energy Accelerator Research Organization (KEK), Accelerator Laboratory (ACCL), Tsukuba, Ibaraki (Japan)

Description

The main ring magnet power supply for the proton accelerator began construction in 1974 and started operation in 1975. In 2012, 38 years later, it was completely dismantled, including the building, to make way for the construction of a cooling water machinery building for SKEKB. The equipment contained trace amounts of PCBs and asbestos, and asbestos was also used in the building itself, due to the era of construction. Other PS facilities were constructed around the same time. This was one of the first large-scale dismantling projects for an accelerator facility. The dismantling details are presented in as much detail as possible to serve as a reference for future dismantling of PS equipment. (J.P.N.)

Abstract (Japanese)

陽子加速器主リング電磁石電源は1974年より建設を始め、75年より通電を開始した設備である。SKEKB用の冷却水機械棟建設のため38年後の2012年に建屋を含め全面解体を行った。年代的に微量PCBやアスベストを含有した機器が存在し建屋自体にもアスベストが使用されている。他のPS 設備もほぼ同じ年代の建設である。これらの設備に対して加速器施設として行うほぼ最初の大規模解体の例となった。これからのPS設備解体の参考に解体内容等出来るだけ詳細に示す。(著者)
Part of:
Proceedings of the meeting on the technical study at KEK

Additional details

Additional titles

Original title (Japanese)
陽子加速器主リング電磁石電源の解体

Publishing Information

Imprint Pagination
55 p.
Journal Page Range
p. 27-31
Report number
KEK-PROC--2014-12

Conference

Title
Meeting on the technical study at KEK
Dates
4 Nov 2014
Place
Tsukuba, Ibaraki (Japan)

Optional Information

Notes
5 figs., 2 tabs.; Article title and abstract translated from Japanese in support of AI Imprint:2014#5E74##5EA6# #6280##8853##4EA4##6D41##4F1A##5831##544A##96C6#