Published January 2001 | Version v1
Report Open

Experiences and lessons learnt on staffing from the first Indian nuclear power plant (PHWR)

  • 1. Nuclear Power Corporation of India Ltd, V.S. Bhavan, Anushaktinagar, Mumbai (India)

Description

Three decades of operating experience in India has led to sustained high performance of NPPs. The staffing modules and policies are standardised. The basic functions of operation, maintenance, technical support and quality assurance are carried out by a team of 727 in-plant persons (for a 2 x 220 MW PHWR station) organised at five levels, for fifty positions in ten job families. Specific qualification levels apply to each position - six at management positions, five licensed positions with the rest qualified through an equivalent training scheme. Practically all O and M activities are carried out on-site by the utility manpower with minimum involvement of contractors. The entire process of human resource development is in-house - with each NPP organisation comprised of 30% experienced staff transferred from older NPPs and 70% totally developed out of fresh recruits. Four to eight years lead time goes to qualify fresh recruits depending on the position. This optimisation of manpower is a result of continuous learning - through operating experience and regulatory feed back and self assessment for (i) optimising quantum of work load and (ii) improving productivity. For the first category, design improvements over older NPP's increased reliability, operability, maintainability and human factors are described separately in the companion paper. In this paper the organisation factors are discussed, starting with the initial lessons that demanded improved management and enhanced quality programmes and caused temporarily, high demand of staffing for bringing out new systems, e.g., (i) attaining maturity of units; (ii) standardising training, retraining and cross training and qualifications; (in) job rotations, (iv) in service inspection of reactor components; (v) quality audits. The experiences on subsequent optimisation of staffing levels are outlined. (author)

Files

32004231.pdf

Files (199.1 kB)

Name Size Download all
md5:6f26461f7ac079ade466258e09d2555a
199.1 kB Preview Download
Part of:
Staffing requirements for future small and medium reactors (SMRs) based on operating experience and projections

Additional details

Publishing Information

Imprint Title
Staffing requirements for future small and medium reactors (SMRs) based on operating experience and projections
Imprint Pagination
129 p.
Journal Page Range
p. 47-58
ISSN
1011-4289
Report number
IAEA-TECDOC--1193

INIS

Country of Publication
International Atomic Energy Agency (IAEA)
Country of Input or Organization
International Atomic Energy Agency (IAEA)
INIS RN
32004231
Subject category
S21: SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS;
Descriptors DEI
ECONOMICS; HUMAN FACTORS; IN-SERVICE INSPECTION; PERSONNEL MANAGEMENT; PHWR TYPE REACTORS; PRODUCTIVITY; REACTOR MAINTENANCE; REACTOR OPERATION; REACTOR OPERATORS; STANDARDIZATION; TRAINING
Descriptors DEC
EDUCATION; HEAVY WATER COOLED REACTORS; HEAVY WATER MODERATED REACTORS; INSPECTION; MAINTENANCE; MANAGEMENT; OPERATION; PERSONNEL; REACTORS

Optional Information

Notes
1 fig., 6 tabs