BWR In-Core Monitor Housing Replacement Under Dry Condition of Reactor Pressure Vessel

  • 1. Japan Atomic Power Company (Japan)
  • 2. Hitachi Ltd. (Japan)
  • 3. General Electric International Inc. (Japan)
  • 4. General Electric Company (United States)

Description

A new method of In-Core Monitor Housing replacement has been successfully applied to Tokai Unit 2 (BWR with 1100 MWe) in April of 2001. It was designed to replace a housing under dry condition of reactor pressure vessel (RPV): this enabled the elimination of water filled-up and drained processes during the replacement procedure resulting in the reduction of implementation schedule. To realize the dry condition, the radiation shields were placed in the RPV and the hollow guide pipe (GP) was adopted to transfer the apparatuses from the top to the bottom work area. (authors)

Additional details

Publishing Information

Publisher
American Society of Mechanical Engineers - ASME
Imprint Place
New York (United States)
Imprint Pagination
6 p.

Conference

Title
10. international conference on nuclear engineering
Acronym
ICONE 10
Dates
14-18 Apr 2002
Place
Arlington - Virginia (United States)

INIS

Country of Publication
United States
Country of Input or Organization
France
INIS RN
39077135
Subject category
S21: SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS;
Resource subtype / Literary indicator
Conference
Descriptors DEI
BWR TYPE REACTORS; EQUIPMENT; IMPLEMENTATION; MONITORS; PRESSURE VESSELS; SCHEDULES; SHIELDS; WATER
Descriptors DEC
CONTAINERS; ENRICHED URANIUM REACTORS; HYDROGEN COMPOUNDS; MEASURING INSTRUMENTS; OXYGEN COMPOUNDS; POWER REACTORS; REACTORS; THERMAL REACTORS; WATER COOLED REACTORS; WATER MODERATED REACTORS