The Completion of SPEAR 3

Description

On December 15, 2003, 8 1/2 months after the last electrons circulated in the old SPEAR2 storage ring and 5 days after the beginning of commissioning, the first electrons were accumulated in the completely new SPEAR 3 ring. By January 22, the first 100-mA beam was stored, preparing the path for delivering beam to users in early March of this year. The rapid installation and commissioning are a testimony to the SPEAR 3 project staff and collaborators who have built an excellent machine and equipped it with powerful and accessible machine modeling and control programs. The final year of component fabrication, the 7-month installation period, and present-day SPEAR 3 operation are described

Availability note (English)

Available from PURL: https://www.osti.gov/servlets/purl/839848-VzT275/native/

Additional details

Publishing Information

Imprint Pagination
4 p.
Report number
SLAC-PUB--11117

INIS

Country of Publication
United States
Country of Input or Organization
United States
INIS RN
36097953
Subject category
S43: PARTICLE ACCELERATORS;
Resource subtype / Literary indicator
Non-conventional Literature
Descriptors DEI
COMMISSIONING; ELECTRONS; FABRICATION; SIMULATION; SPEAR; STORAGE RINGS
Descriptors DEC
ELEMENTARY PARTICLES; FERMIONS; LEPTONS; STORAGE RINGS

Optional Information

Contract/Grant/Project number
AC--02-76SF00515
Funding organization
USDOE Office of Science (United States)