Study of decommissioning cost evaluation technique for nuclear reactor dismantlement. Calculation of decommissioning cost by COSMARD

  • 1. Japan Atomic Energy Research Inst., Tokai Research Establishment, Tokai, Ibaraki (Japan)
  • 2. Japan Atomic Energy Research Inst., Kashiwa, Chiba (Japan)

Description

A model for estimating decommissioning costs consisting of labor cost, device cost and expense, was developed for items which OECD/NEA had standardized, and was installed into the computer system for planning and management of reactor decommissioning (COSMARD). Input data files and databases for the decommissioning of JPDR were prepared, and the decommissioning cost was calculated with COSMARD. In addition, the decommissioning cost for a large scale BWR power plant was also calculated on the assumption of the advantage of scale. The calculations have shown that it is useful and efficient for studying the decommissioning costs for nuclear reactors to apply the COSMARD with database for cast estimation to the decommissioning cost calculation. (author)

Availability note (English)

Available from JAEA; DOI: https://doi.org/10.11484/jaeri-tech-2005-046

Files

37022206.pdf

Files (1.7 MB)

Name Size Download all
md5:33dd7da1c053ef6115784968d4d77981
1.7 MB Preview Download

System files (126.1 kB)

Name Size Download all

Additional details

Identifiers

Publishing Information

Imprint Pagination
57 p.
Report number
JAERI-Tech--2005-046

Optional Information

Notes
10 refs., 20 figs., 16 tabs.