Published June 2015 | Version v1
Journal article

Assessment of control room habitability and unfiltered air inleakage test of the OPR 1000 NPP

  • 1. Central Research Institute, Korea Hydro and Nuclear Power Co., Ltd., Daejeon (Korea, Republic of)

Description

The assessment of control room habitability for Hanbit unit 5 was performed based on GL 2003-01 and Regulatory Guide 1.197. The integrated control room envelope (CRE) test was performed utilizing ASTM E741. Four tests were performed using each of the control room HVAC subtrains. The control room heating, ventilating, and air conditioning (HVAC) system lineup of pressurization mode test was based upon a lineup that encompassed the design basis radiological analyses. The other control room HVAC system lineup of isolation mode test was based on an operation mode that considers toxic gas. The measured inleakage for the isolation test mode remains within the toxicity limit. Radiation effect analysis showed that the measured inleakage satisfied the regulatory criteria, and the inleakage would not result in control room operator dose exceeding 50 mSv whole body and 500 mSv thyroid except train A pressurization test mode. The thyroid dose due to maximum measured unfiltered inleakage of 8976 lpm for train A is corresponding to 700 mSv. Modifications to the CRE boundary and control room HVAC system should be done to demonstrate that the measured unfiltered inleakage for train A pressurization test mode is bounded by the regulatory criteria assumed in the design basis radiological analyses. (author)

Availability note (English)

Available from http://dx.doi.org/10.1080/00223131.2014.995145

Additional details

Identifiers

Publishing Information

Journal Title
Journal of Nuclear Science and Technology (Tokyo)
Journal Volume
52
Journal Issue
6
Journal Page Range
p. 905-911
ISSN
0022-3131

Optional Information

Notes
9 refs., 4 figs., 2 tabs.