Feedback of the Licensing Process of the First Nuclear Installation in Fusion, ITER

  • 1. ITER Organization, St-Paul-lez-Durance (France)

Description

Full text: After the submission of Preliminary Safety Report (PSR) in March 2010 by the ITER Organization, the safety French authorities started an intensive and detailed examination led by its technical support IRSN (Institut de Radioprotection et de Surete Nuclaire). Sixteen months later, in December 2011, the standing group (composed by expert members in different field of nuclear safety) concluded that the measures elaborated by IO in their PSR are satisfactory on the whole and therefore gave a favourable advice for the creation of the Installation. The IO must still consolidate the design of some equipment and provide further information on various issues within a period of two years. The standing group would thus like to examine the additional information provided before the start of the tokamak equipment assembly phase. (author)

Part of:
24. IAEA Fusion Energy Conference. Programme and Book of Abstracts

Additional details

Publishing Information

Imprint Title
24. IAEA Fusion Energy Conference. Programme and Book of Abstracts
Imprint Pagination
789 p.
Journal Page Range
p. 608
Report number
IAEA-CN--197

Conference

Title
24. IAEA Fusion Energy Conference
Acronym
FEC 2012
Dates
8-13 Oct 2012
Place
San Diego, CA (United States)

INIS

Country of Publication
International Atomic Energy Agency (IAEA)
Country of Input or Organization
International Atomic Energy Agency (IAEA)
INIS RN
45034027
Subject category
S70: PLASMA PHYSICS AND FUSION TECHNOLOGY;
Resource subtype / Literary indicator
Conference
Descriptors DEI
DESIGN; EQUIPMENT; FEEDBACK; FRANCE; ITER TOKAMAK; NUCLEAR FACILITIES; RADIATION PROTECTION; SAFETY REPORTS
Descriptors DEC
CLOSED PLASMA DEVICES; DEVELOPED COUNTRIES; EUROPE; THERMONUCLEAR DEVICES; THERMONUCLEAR REACTORS; TOKAMAK DEVICES; TOKAMAK TYPE REACTORS; WESTERN EUROPE

Optional Information