Gentilly-2 refurbishment project

Creators

  • 1. Hydro-Quebec, Gentilly-2 Nuclear Generating Station, Montreal, Quebec (Canada)

Description

This paper discusses the refurbishment project for Gentilly-2 CANDU nuclear power plant. Gentilly-2 was commercially commissioned in October 1983 and has seen 21 years of operation. It is now entering a second cycle of production. The refurbishment involves safety and licensing' reactor core refurbishment, engineering, environmental government authorizations, planning and costs control

Part of:
CANDU life cycle management workshop on 'HTS aging management'. Proceedings

Additional details

Publishing Information

Publisher
Canadian Nuclear Society
Imprint Place
Toronto, Ontario (Canada)
Imprint Title
CANDU life cycle management workshop on 'HTS aging management'. Proceedings
Imprint Pagination
92.8 Megabytes
Journal Page Range
[20 p.]

Conference

Title
CANDU life cycle management workshop on 'HTS aging management'
Dates
21-22 Feb 2005
Place
Oshawa, Ontario (Canada)

Optional Information

Notes
Slide presentation only.