AVR nuclear test power plant. 3. and 4. Quarterly report 1979 (1.7.1979 - 31.12.1979)

Description

Automatic translation: After approval, the power plant went into the first phase of recommissioning approached by the supervisory authority on August 9th. In view of the short operating time and that in the initial phase low electrical performance were for the reporting quarter the following operating data is achieved: - Time availability el. - 3/79 29.6% - Availability of work el. - 3/79 12.8% - Gross work el. 3/79 - 4231.4 MWh Further important operating data for the third quarter of 1979 can be found in the appendix compiled.

Abstract (German)

Das Kraftwerk wurde nach Zustimmung zur ersten Phase der Wiederinbetriebnahme durch die Aufsichtsbehoerde am 9. August angefahren. In Anbetracht der kurzen Betriebszeit und der in der Anfangsphase niedrigen elektrischen Leistung wurden für das Berichtsquartal folgende Betriebsdaten erreicht: - Zeitverfügbarkeit el. - 3/79 29,6 % - Arbeitsverfügbarkeit el. - 3/79 12,8 % - Bruttoarbeit el. 3/79 - 4231,4 MWh Weitere wichtige Betriebsdaten des 3. Quartals 1979 sind im Anhang zusammengestellt.

Files

Restricted

The record is publicly accessible, but files are restricted to users with access.

Additional details

Additional titles

Original title (German)
AVR Atomversuchskraftwerk. 3. und 4. Quartalsbericht 1979 (1.7.1979 - 31.12.1979)

Publishing Information

Imprint Pagination
75 p.
Report number
INIS-DE--21M1377

INIS

Optional Information

Notes
Document from Juelich Preservation Project; 11 figs., 8 tabs.