State of opening the cover and carrying out the checkup of the reactor vessel of the nuclear-powered ship 'Mutsu' by Japan Atomic Energy Research Institute

Description

In the checkup by opening the cover of the reactor vessel of the nuclear-powered ship 'Mutsu', Japan Atomic Energy Research Institute carried out the checkup and maintenance for the reactor proper, control system and primary coolant facilities including the secondary side of steam generators and the pressure balancing valve of the containment vessel. The works were classified into the opening of the reactor, checkup, maintenance and restoration. The opening was begun on August 4, 1988, and finished on December 5. The checkup and maintenance were begun on September 22, and are still continued now. The maximum radiation dose rate on the surfaces of fuel assemblies and control rods and at the positions 1 m distant from them was measured. The results of the checkup of various components are reported. In 290 absorbent rods of control rods, spot corrosion and discoloration were observed, of which the spot corrosion penetrated the walls of 4 rods. Also in 12 fuel rods, spot corrosion was observed near the welded end plugs, but leak was not observed. (K.I.)

Additional details

Publishing Information

Journal Title
Genshiryoku Anzen Iinkai Geppo
Journal Issue
no.124
Series
Genshiryoku Anzen Iinkai Geppo.
CODEN
GAIGD