Published April 1984 | Version v1
Journal article

Retro-fitting measures completed early at Brunsbuettel nuclear power station - with particular emphasis on pipework

Creators

  • 1. Kraftwerk Union A.G., Offenbach am Main (Germany, F.R.)

Description

The execution of the retro-fitting measures carried out at Brunsbuettel nuclear power station was determined by the critical path of the pipework installation, which claimed about 75% of the total outage time. If all the technical requirements are known from the outset and not changed during the execution of the work, it is possible with the consequent utilization of experience of all participants to adhere to the contractual conversion programme. After an outage time of about 12 months it was possible in this way to bring Brunsbuettel nuclear power station back into commercial operation. (orig.)

Abstract (German)

Die Abwicklung der im Kernkraftwerk Brunsbuettel durchgefuehrten Nachruestungsmassnahmen wurde bestimmt durch den terminkritischen Pfad der Rohrleitungsmontagen, die rund 75% der gesamten Stillstandszeit beanspruchten. Wenn alle technischen Voraussetzungen zu Anfang bekannt sind und waehrend der Ausfuehrungen nicht geaendert werden, ist es in Verbindung mit der konsequenten Nutzung aller Erfahrungen aus den vorangegangenen Nachruestungen und dem engagierten Einsatz aller Beteiligten moeglich, den vertraglichen Umruestzeitraum einzuhalten. Das Kernkraftwerk Brunsbuettel konnte dadurch nach rund 12 Monaten Stillstandszeit den Leistungsbetrieb wieder aufnehmen. (orig.)

Additional details

Additional titles

Original title (German)
Nachruestmassnahmen im Kernkraftwerk Brunsbuettel vorzeitig abgeschlossen - Schwerpunkt Rohrleitungen

Publishing Information

Journal Title
VGB Kraftwerkstech.
Journal Volume
64
Journal Issue
4
Series
CODEN: VGBKB.;VGB Kraftwerkstech.
Journal Page Range
276-279
ISSN