Acceptance Test Procedure for New Pumping Instrumentation and Control Skid ''V''
Creators
Description
This Acceptance Test Procedure (ATP) verifies proper construction per the design drawings and tests for proper functioning of the Pumping Instrumentation and Control (PIC) skid ''V''. The scope section lists the systems and functions to be checked. This ATP will be performed at the Site Fabrication Services (SFS) shop upon completion of the construction of the PIC skid
Availability note (English)
Available from INIS in electronic form; Also available from OSTI as DE00804240; PURL: https://www.osti.gov/servlets/purl/804240-gq3xLu/webviewable/
Files
Additional details
Identifiers
Publishing Information
- Imprint Pagination
- 60 p.
- Report number
- RPP--6201/Rev.1
INIS
- Country of Publication
- United States
- Country of Input or Organization
- United States
- INIS RN
- 34022507
- Subject category
- S12: MANAGEMENT OF RADIOACTIVE WASTES, AND NON-RADIOACTIVE WASTES FROM NUCLEAR FACILITIES;
- Descriptors DEI
- DESIGN; MEASURING INSTRUMENTS; MONITORING; PERFORMANCE TESTING; PUMPING; PUMPS; RADIOACTIVE WASTES; STORAGE FACILITIES
- Descriptors DEC
- EQUIPMENT; MATERIALS; RADIOACTIVE MATERIALS; TESTING; WASTES
Optional Information
- Contract/Grant/Project number
- EDN-629587; AC27-99RL14047
- Funding organization
- USDOE Office of Environmental Management (EM) (United States)