Published December 1984
| Version v1
Journal article
Mounting reactor components
Creators
Description
Main features of mounting the Chernobylsk-4 power unit are briefly described. The metal structures are subjected to preliminary assembly at the construction site and then are transported to the reactor building by means of a crane. Preparatory and mounting operations are described for the bottom Water and steam-water lines, steam separators, as well as modernization of a gantry crane for transporting metal structures and supplying large building blocks (up to 50 t wt.) for erecting the central room
Additional details
Additional titles
- Original title (Russian)
- Монтаж оборудования реакторного отделения
Publishing Information
- Journal Title
- Ehnerg. Stroit.
- Journal Issue
- no.12
- Series
- Ehnerg. Stroit.
INIS
- Country of Publication
- USSR
- Country of Input or Organization
- USSR
- INIS RN
- 16072183
- Subject category
- S21: SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS;
- Descriptors DEI
- CHERNOBYLSK-4 REACTOR; CONSTRUCTION; CRANES; NUCLEAR POWER PLANTS; STEAM LINES; STEAM SEPARATORS
- Descriptors DEC
- ENRICHED URANIUM REACTORS; EQUIPMENT; GRAPHITE MODERATED REACTORS; LWGR TYPE REACTORS; MATERIALS HANDLING EQUIPMENT; NUCLEAR FACILITIES; PIPELINES; POWER PLANTS; POWER REACTORS; REACTORS; REMOTE HANDLING EQUIPMENT; THERMAL POWER PLANTS; THERMAL REACTORS; VAPOR SEPARATORS; WATER COOLED REACTORS