Special Analyses for the Hanford Integrated Disposal Facility Performance Assessment - 20102

  • 1. ORANO Federal Services, LLC (United States)
  • 2. INTERA, Inc. (United States)

Description

In 2014, the Department of Energy (DOE) Office of River Protection and its contractors began to develop a performance assessment for the near-surface disposal of low-level and mixed low-level waste at the Hanford Site's Integrated Disposal Facility (IDF). The IDF is a doubly-lined landfill that was constructed between 2004 and 2006 to be the disposal facility for the vitrified low-activity waste that will be produced at the Waste Treatment and Immobilization Plant (WTP). IDF is also expected to receive solid secondary waste produced at the WTP and other solid wastes from site activities. The IDF has been in a preoperational state awaiting authorization from DOE and a RCRA permit modification from the State of Washington Department of Ecology to receive waste. Both the Disposal Authorization Statement and permit modification require a performance assessment demonstrating that the system of engineered and natural features will limit releases of radionuclides and hazardous chemicals from the IDF and be protective of human health and the environment. The simulated duration is 10,000 years. Based on the analyses presented in the 2017 Integrated Disposal Facility Performance Assessment, DOE issued a conditional Operating Disposal Authorization Statement for the IDF in June 2018. The long-term performance of the IDF to be protective of human health and the environment was evaluated under the requirements of DOE Order 435.1, Radioactive Waste Management. Computer simulations were performed to evaluate whether or not the IDF would comply with DOE requirements. In the time that has passed since the performance assessment was approved by DOE, new information has been discovered that had not been considered in the performance assessment. Since this new information has not been evaluated, the potential impact of the changes have not been taken into consideration in DoE's disposal authorization. DOE and its contractors follow a change control process to screen and, when necessary, evaluate new information that could potentially impact the conclusions of the completed performance assessment. This paper will describe the change control process and provide two examples of evaluations performed following the change control process. The first example evaluates a new waste form for liquid secondary waste that was not evaluated in the performance assessment. In the performance assessment, liquid secondary waste was assumed to be solidified with grout. A new recommendation to dispose of the liquid secondary waste after drying it to a powder was evaluated. The second example evaluates inventory implications from changes to the flow sheet that estimates the feed composition to the low-activity waste vitrification facility. The changes result in higher strontium concentrations in the vitrified waste stream. (authors)

Availability note (English)

Available from: WM Symposia, Inc., PO Box 27646, 85285-7646 Tempe, AZ (US)

Additional details

Publishing Information

Imprint Pagination
37 p.
Report number
INIS-US--21-WM-20102

Conference

Title
46. Annual Waste Management Conference
Acronym
WM2020
Dates
8-12 Mar 2020
Place
Phoenix, AZ (United States)

Optional Information

Notes
11 refs.; available online at: https://www.xcdsystem.com/wmsym/2020/index.html