Operation of the SPring-8 SR main magnet power supplies and control system
Creators
- 1. JAERI-RIKEN SPring-8 Project Team, Kamigori, Hyogo (Japan)
Description
After installation of the power supplies (PSs) of the main magnets in the SPring-8 Storage Ring (SR) in 1995, cable connections between the PSs and the magnets were completed in October of 1996. The final test operation and inspection of current stability, ripple measurement and control, interlock sequence and operation program were successfully carried out by March of 1996. During the SR beam commissioning and operations for the beam line users from March to July of 1997, the magnet power supply were operated successfully. (author)
Additional details
Publishing Information
- Publisher
- Japan Synchrotron Radiation Research Inst, JASRI
- Imprint Place
- Kamigori, Hyogo (Japan)
- Imprint Title
- Proceedings of the 11th symposium on accelerator science and technology
- Imprint Pagination
- 563 p.
- Journal Page Range
- p. 395-398
Conference
- Title
- 11. symposium on accelerator science and technology
- Dates
- 21-23 Oct 1997
- Place
- Kamigori, Hyogo (Japan)
INIS
- Country of Publication
- Japan
- Country of Input or Organization
- Japan
- INIS RN
- 30002295
- Subject category
- S43: PARTICLE ACCELERATORS;
- Resource subtype / Literary indicator
- Conference
- Descriptors DEI
- BEAM BENDING MAGNETS; BEAM FOCUSING MAGNETS; CONTROL SYSTEMS; INTERLOCKS; NOISE; OPERATION; POWER SUPPLIES; SPRING-8 STORAGE RING; STABILITY; START-UP
- Descriptors DEC
- ELECTRONIC EQUIPMENT; EQUIPMENT; MAGNETS; RADIATION SOURCES; STORAGE RINGS; SYNCHROTRON RADIATION SOURCES