Published October 29, 1976 | Version v1
Report

Status of the tube elongation problem as of June 1976

Description

It was discovered in May of 1971 that the N Reactor process tubes had apparently increased in length by as much as one inch. Preliminary observations and measurements led to the tentative conclusion that this observed elongation was linear with accumulated tube exposure and also that it was related in some manner to the tube fabrication process. It appeared that the observed elongation was approximately proportional to the degree of cold work retained in the finished tubes. This latter conclusion was based on the observation that those tubes with approximately 17-18 percent cold work had elongated only about half as much as the standard 30-percent-cold-worked tubes. It was immediately recognized that if such elongation was to continue unchecked it could pose a limit to reactor life since total possible tube expansion, from all causes, is limited to 1.75 inches by nozzle design considerations as shown in Figure 1. Thermal and hydraulic expansion were calculated to total approximately 0.75 inches which left only one inch available to accommodate tube growth or creep. Since discovery of this phenomenon, an extensive measurements program has been carried out to evaluate the extent and rate of tube elongation. Two corrective approaches have been developed and a small number of tubes were modified by each method during the 1976 summer outage. During the 1974, 1975 and 1976 Summer Outages, measurements were made on all tubes to determine the clearance remaining between the nozzle keys and the gas packing ring. These readings not only give an overall picture of the extent of elongation, but also provide immediate data indicating which tubes are about out of clearance. The report presents an evaluation of the measurements taken to date

Availability note (English)

MF available from INIS under the Report Number.

Additional details

Publishing Information

Imprint Pagination
47 p.
Report number
UNI--686

Optional Information

Notes
Available from NTIS. $4.00.