Report of the ANS Project Feasibility Workshop for a High Flux Isotope Reactor-Center for Neutron Research Facility
Description
The Advanced Neutron Source (ANS) Conceptual Design Report (CDR) and its subsequent updates provided definitive design, cost, and schedule estimates for the entire ANS Project. A recent update to this estimate of the total project cost for this facility was $2.9 billion, as specified in the FY 1996 Congressional data sheet, reflecting a line-item start in FY 1995. In December 1994, ANS management decided to prepare a significantly lower-cost option for a research facility based on ANS which could be considered during FY 1997 budget deliberations if DOE or Congressional planners wished. A cost reduction for ANS of about $1 billion was desired for this new option. It was decided that such a cost reduction could be achieved only by a significant reduction in the ANS research scope and by maximum, cost-effective use of existing High Flux Isotope Reactor (HFIR) and ORNL facilities to minimize the need for new buildings. However, two central missions of the ANS -- neutron scattering research and isotope production-were to be retained. The title selected for this new option was High Flux Isotope Reactor-Center for Neutron Research (HFIR-CNR) because of the project's maximum use of existing HFIR facilities and retention of selected, central ANS missions. Assuming this shared-facility requirement would necessitate construction work near HFIR, it was specified that HFIR-CNR construction should not disrupt normal operation of HFIR. Additional objectives of the study were that it be highly credible and that any material that might be needed for US Department of Energy (DOE) and Congressional deliberations be produced quickly using minimum project resources. This requirement made it necessary to rely heavily on the ANS design, cost, and schedule baselines. A workshop methodology was selected because assessment of each cost and/or scope-reduction idea required nearly continuous communication among project personnel to ensure that all ramifications of propsed changes
Availability note (English)
MF available from INIS under the Report Number; Also available from OSTI as DE95017192; NTIS; US Govt. Printing Office Dep.
Files
Additional details
Publishing Information
- Imprint Pagination
- 30 p.
- Report number
- ORNL/TM--13005
INIS
- Country of Publication
- United States
- Country of Input or Organization
- United States
- INIS RN
- 27019920
- Subject category
- S21: SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS;
- Resource subtype / Literary indicator
- Numerical Data
- Descriptors DEI
- COMPILED DATA; COST; DESIGN; HFIR REACTOR; NEUTRON SOURCE FACILITIES; SCHEDULES
- Descriptors DEC
- DATA; ENRICHED URANIUM REACTORS; INFORMATION; IRRADIATION REACTORS; ISOTOPE PRODUCTION REACTORS; NUMERICAL DATA; REACTORS; RESEARCH AND TEST REACTORS; RESEARCH REACTORS; TANK TYPE REACTORS; TEST FACILITIES; TEST REACTORS; THERMAL REACTORS; WATER COOLED REACTORS; WATER MODERATED REACTORS
Optional Information
- Contract/Grant/Project number
- Contract AC05-84OR21400
- Funding organization
- USDOE, Washington, DC (United States).