How to forecast nuclear plant construction time

Description

A cumulative probability distribution curve is described which can help planners estimate the construction time for nuclear power plants. Accumulated construction data published by the Nuclear Regulatory Commission in Construction Status Report - Nuclear Power Plants is the basis for the curves. A case for both optimism and pessimism in lead times can be argued, but a probability curve can be drawn by monitoring construction duration trends and forming a histogram on which to base cumulative probability. The curve can be adapted to project the time for a project already in progress. 6 figures

Additional details

Publishing Information

Journal Title
Electr. Light Power (Boston)
Journal Volume
58
Journal Issue
4
Series
Electr. Light Power (Boston).
Journal Page Range
32, 35
ISSN
0013-4120

INIS

Country of Publication
United States
Country of Input or Organization
United States
INIS RN
11553126
Subject category
S29: ENERGY PLANNING, POLICY AND ECONOMY;
Descriptors DEI
CONSTRUCTION; FORECASTING; NUCLEAR POWER PLANTS; PLANNING
Descriptors DEC
NUCLEAR FACILITIES; POWER PLANTS; THERMAL POWER PLANTS