Operational reliability of the Point Lepreau GS standby generators
Creators
- 1. Safety and Compllance Group, New Brunswick Electric Power Commission, Point Lepreau Generating Station, P.O.Box 10 Lepreau, New Brunswick E0G 2H0 (Canada)
Description
Performance of the two Point Lepreau GS standby generators during the first three years of licensed station operation is reviewed. It is shown that the mandated reliability/availability requirements have been met. The nature of starting and running failures has been examined and the consequences, in terms of design and procedural changes, discussed. A brief review of standby generator outages is included to permit estimates of standby generator availability and total Class III standby power unavailability. A pair of simple equations is introduced as a means of estimating the probable economic penalty, both cumulative and incremental, associated with the running failure of one standby generator while the other is on a maintenance outage. (authors)
Files
47076526.pdf
Files
(505.1 kB)
| Name | Size | Download all |
|---|---|---|
|
md5:4a1f1040eb7482655251702d735fd008
|
505.1 kB | Preview Download |
Additional details
Publishing Information
- Imprint Title
- Operating experience relating to on-site electric power sources. Proceedings of a Specialist Meeting
- Imprint Pagination
- 399 p.
- Journal Page Range
- p. 249-262
- Report number
- NEA-CSNI-R--1986-115
Conference
- Title
- CSNI specialist meeting on operating experience relating to on-site electric power sources
- Dates
- 16-18 Oct 1985
- Place
- London (United Kingdom)
INIS
- Country of Publication
- Nuclear Energy Agency of the OECD (NEA)
- Country of Input or Organization
- Nuclear Energy Agency of the OECD (NEA)
- INIS RN
- 47076526
- Subject category
- S42: ENGINEERING; S21: SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS;
- Resource subtype / Literary indicator
- Conference, Numerical Data
- Descriptors DEI
- AVAILABILITY; COST ESTIMATION; ELECTRIC GENERATORS; FAILURE MODE ANALYSIS; IN-SERVICE INSPECTION; MAINTENANCE; ON-SITE POWER GENERATION; OUTAGES; POINT LEPREAU-1 REACTOR; PROBABILISTIC ESTIMATION; RELIABILITY; SPECIFICATIONS; START-UP; STATISTICAL DATA; TESTING
- Descriptors DEC
- CALCULATION METHODS; CANDU TYPE REACTORS; DATA; ELECTRICAL EQUIPMENT; EQUIPMENT; HEAVY WATER COOLED REACTORS; HEAVY WATER MODERATED REACTORS; INFORMATION; INSPECTION; NATURAL URANIUM REACTORS; NUMERICAL DATA; PHWR TYPE REACTORS; POWER GENERATION; POWER REACTORS; PRESSURE TUBE REACTORS; REACTORS; SYSTEM FAILURE ANALYSIS; SYSTEMS ANALYSIS; THERMAL REACTORS
Optional Information
- Notes
- 1 ref.