Published February 1980 | Version v1
Report Open

Sodium fill of FFTF

Description

With construction of the Fast Flux Test Facility (FFTF) completed, the first major objective in the startup program was to fill the sodium systems. A sodium fill sequence was developed to match construction completion, and as systems became available, they were inerted, preheated, and filled with sodium. The secondary sodium systems were filled first while dry refueling system testing was in progress in the reactor vessel. The reactor vessel and the primary loops were filled last. This paper describes the methods used and some of the key results achieved for this major FFTF objective

Availability note (English)

MF available from INIS under the Report Number; Available from NTIS., PC A02/MF A01.

Files

11566083.pdf

Files (943.8 kB)

Name Size Download all
md5:64fc4da983e33e950065b155176b7708
943.8 kB Preview Download

Additional details

Publishing Information

Imprint Pagination
16 p.
Report number
HEDL-SA--2107-F

Conference

Title
2. international conference of liquid metal technology for energy systems.
Dates
20 - 24 Apr 1980.
Place
Richland, WA, USA.

Optional Information

Secondary number(s)
CONF-800401--27.