Overload handling of IBT using load and capacitor shedding

  • 1. Department of Electrical Engineering, Faculty of Engineering, Universitas Indonesia, Depok, 16424 (Indonesia)

Description

Faulted Inter Bus Transformer (IBT) can cause power system instability. Therefore, it will be isolated to prevent the spreading of disturbance. IBT at the Ptn Substation which supplies Ptn – Grt and Dwt Subsystem is discussed in this paper. The event discussed is 2 of 3 IBTs are out of work so that only one left. So, load shedding of Dwt Subsystem is required to avoid further disturbance. However, after it is applied, the voltage at the Dwt Subsystem will increase beyond the allowed rating. Therefore, further action is required by releasing some capacitor banks of several substations that have the highest rated voltage until the voltage in all substations is within the permitted rating. Finally, The system return to stable after load shedding with total 226.45 MW and capacitor shedding with total 150 Mvar. (paper)

Availability note (English)

Available from http://dx.doi.org/10.1088/1757-899X/673/1/012056

Additional details

Publishing Information

Journal Title
IOP Conference Series. Materials Science and Engineering (Online)
Journal Volume
673
Journal Issue
1
Journal Page Range
[10 p.]
ISSN
1757-899X

Conference

Title
International Conference on Broad Exposure to Science and Technology 2019
Acronym
BEST2019
Dates
7-8 Aug 2019
Place
Bali (Indonesia)

INIS

Country of Publication
United Kingdom
Country of Input or Organization
International Atomic Energy Agency (IAEA)
INIS RN
54076117
Subject category
S42: ENGINEERING;
Resource subtype / Literary indicator
Conference
Descriptors DEI
CAPACITORS; ELECTRIC POTENTIAL; INSTABILITY; PERFORMANCE; POWER SYSTEMS; TRANSFORMERS
Descriptors DEC
ELECTRICAL EQUIPMENT; ENERGY SYSTEMS; EQUIPMENT