Results of second regular inspection of No.3 plant in the Takahama Power Station, Kansai Electric Power Co., Inc

Creators

Description

The second regular inspection of No.3 plant in the Takahama Power Station was carried out from March 20 to June 11, 1987. The parallel operation was resumed on May 21, 1987, 63 days after the parallel off. The facilities as the object of inspection were the reactor proper, reactor cooling system, measurement and control system, fuel facilities, radiation control facilities, waste facilities, reactor containment installation, and emergency power generation system. On these facilities as the object of inspection, the appearance, disassembling, leak, function, performance and other inspections were carried out. As the result, abnormality was not found at all. The works related to this regular inspection were accomplished within the range of allowable radiation dose based on the relevant laws. Major reconstruction work was not carried out during the period of this regular inspection. (Kako, I.)

Additional details

Publishing Information

Journal Title
Genshiryoku Anzen Iinkai Geppo
Journal Issue
no.107
Series
Genshiryoku Anzen Iinkai Geppo.
CODEN
GAIGD