Published 1998 | Version v1
Book

Full system decontamination at Fukushima-Daiichi Nuclear Power Station

  • 1. Tokyo Electric Power Co., Inc. (Japan)

Description

In Unit No.3 of Fukushima Daiichi Nuclear Power Station, Full System Decontamination was performed for the reactor and reactor recirculation system. Total radioactivity of about 10 TBq as converted to Co-60 was dissolved and removed, while the average dose-equivalent rate of the reactor bottom in water was reduced from 4.07 mSv/h before decontamination to 0.11 mSv/h after decontamination. The target DF20 could therefore be achieved. It was also proved that such a large-scale Full System Decontamination could be completed in exactly one week. In the future, the experiences and data obtained in the course of this work will be disseminated to those concerned when similar large-scale improvement work is to be made with other units. (J.P.N.)

Part of:
1998 JAIF international conference on water chemistry in nuclear power plants, proceedings

Additional details

Publishing Information

Publisher
Japan Atomic Industrial Forum, Inc.
Imprint Place
Tokyo (Japan)
Imprint Title
1998 JAIF international conference on water chemistry in nuclear power plants, proceedings
Imprint Pagination
972 p.
Journal Page Range
p. 357-362

Conference

Title
1998 JAIF international conference on water chemistry in nuclear power plants
Acronym
Water chemistry '98
Dates
13-16 Oct 1998
Place
Kashiwazaki, Niigata (Japan)