Control room temperature survey at a pressurized water reactor nuclear power station

Creators

  • 1. Flakt, Inc., Winston-Salem, NC (USA)

Description

During preoperational testing at a near term operating license (NTOL) pressurized water reactor power facility, numerous printed circuit board failure and out of calibration instrument loops have been encountered. This, coupled with licensee event reports filed by other operating stations, I. and E. notices, etc., prompted the utility to conduct a survey of various control panels and logic racks in the control room to determine operating temperatures. The completion of all activities associated with this survey are expected to result in longer qualified life for components, less time expended on calibration activities, and more reliable instrument loop indication and operation. This paper discusses the testing methodology and preliminary work performed to give the best possible results

Additional details

Publishing Information

Imprint Title
Proceedings of the 19th DOE/NRC nuclear air cleaning conference
Journal Page Range
p. 1139-1147.
Report number
NUREG/CP--0086-Vol.2

Conference

Title
19. DOE/NRC nuclear air cleaning conference.
Dates
18-21 Aug 1986.
Place
Seattle, WA (USA).

INIS

Country of Publication
United States
Country of Input or Organization
United States
INIS RN
20016486
Subject category
S21: SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS;
Resource subtype / Literary indicator
Conference
Descriptors DEI
CALIBRATION; CONTROL ROOMS; FAILURES; LIFETIME; MICROELECTRONIC CIRCUITS; PERFORMANCE; PWR TYPE REACTORS; REACTOR START-UP; RELIABILITY; TEMPERATURE DEPENDENCE; TESTING
Descriptors DEC
ELECTRONIC CIRCUITS; ENRICHED URANIUM REACTORS; POWER REACTORS; REACTORS; START-UP; THERMAL REACTORS; WATER COOLED REACTORS; WATER MODERATED REACTORS