The replacement of an electromagnetic primary sodium sampling pump in the Fast Flux Test Facility

Description

On November 16, 1984 a leak was discovered in one of the Fast Flux Test Facility (FFTF) Primary Sodium Sampling System electromagnetic pumps. The leak was discovered in the course of routine cell entry to investigate a shorted trace heat element. The purpose of this paper is to describe the circumstances surrounding the occurrence of the leak, the actions taken to replace the damaged pump and the additional steps which were necessary to return the plant to power. In addition, the processes involved in producing the leak are described briefly. The relative ease of recovery from this incident is indicative of the overall feasibility of the Liquid Metal Reactor (LMR) operational concept

Availability note (English)

MF available from INIS under the Report Number; Available from NTIS, PC A02/MF A01; 1 as DE87005458.

Files

Restricted

The record is publicly accessible, but files are restricted to users with access.

Additional details

Publishing Information

Imprint Pagination
20 p.
Report number
HEDL-SA--3292-FP

Conference

Title
Nuclear power plant maintenance meeting.
Dates
23-27 Mar 1986.
Place
Salt Lake City, UT (USA).

Optional Information

Notes
Portions of this document are illegible in microfiche products.