Published 1981
| Version v1
Miscellaneous
Operate-shutdown decision and test policy of safety systems on a nuclear power plant
Creators
- 1. Institut National de Recherche d'Informatique et d'Automatique (INRIA), Domaine de Voluceau, 78 -Rocquencourt (France)
- 2. CEA Centre d'Etudes Nucleaires de Fontenay-aux-Roses, 92 (France). Dept. de Surete Nucleaire
- 3. Armines, 75-Paris. (France)
Description
It is shown that operate-shutdown decision on a main system and test policy in a safety system have to be considered jointly. Two criteria are taken into account: an economic criterion (loss of production) and a risk criterion (risk of accident). A method is described in order to evaluate these two criteria according to given policies and operate-shutdown rules. This method leads to the optimisation of test policies and of operate-shutdown rules. Minimisation of loss of production and risk of accident is determined. (author)
Additional details
Publishing Information
- Imprint Title
- Reliability '81
- Journal Page Range
- p. 5B/4/1-5B/4/11.
Conference
- Title
- 3. National reliability conference.
- Dates
- 29 Apr - 1 May 1981.
- Place
- Birmingham, UK.
INIS
- Country of Publication
- United Kingdom
- Country of Input or Organization
- United Kingdom
- INIS RN
- 13692142
- Subject category
- S61: RADIATION PROTECTION AND DOSIMETRY;
- Resource subtype / Literary indicator
- Conference, Non-conventional Literature
- Descriptors DEI
- NUCLEAR POWER PLANTS; OPTIMIZATION; REACTOR OPERATION; REACTOR SAFETY; REACTOR SHUTDOWN; RISK ANALYSIS
- Descriptors DEC
- NUCLEAR FACILITIES; OPERATION; POWER PLANTS; SAFETY; THERMAL POWER PLANTS