Quebec to have nuclear power by 1980

Creators

Description

The 600 MW Gentilly-2 CANDU PHWR single-unit station is now scheduled to deliver commercial power early in 1980. Differences from the Pickering units include a 400,000 gallon dousing tank (which eliminates the need for a vacuum building), and four 200-ton steam generators arranged in two independent banks, each with two boilers in parallel (compared with 12 boilers per unit at Pickering). Progress with the construction is described. Modifications of Gentilly-1 during shutdown are listed. Gentilly-1 may eventually serve as the prototype for a family of CANDU-BLW stations using recycled plutonium. Startup of the LaPrade heavy-water plant has been rescheduled for 1981. It will draw steam and warmed cooling water from Gentilly-1 and Gentilly-2. (N.D.H.)