Published 2009 | Version v1
Miscellaneous

Restoration to serviceability of Bruce 'A' heat transfer equipment

  • 1. Babcock and Wilcox Canada Ltd., Cambridge, Ontario (Canada)
  • 2. Bruce Power. Ontario (Canada)

Description

Bruce Units 1 to 4 were shut down during the 1990s by the former Ontario Hydro, due in part to a long list of system and equipment deficiencies and concerns, including steam generator tube degradation as a consequence of the then-existing steam generator secondary side water chemistry conditions. Upon its creation in 2001, and following a program of condition assessment, Bruce Power was able to determine that Units 3 and 4 could return to service; but that Units 1 and 2 would require refurbishment. That Refurbishment Program, which is currently well advanced, included the re-assessment of the condition of equipment throughout the plant including the heat transfer equipment; and determination item-by-item as to what inspection, cleaning, repair, or even replacement would be required to put the equipment into a condition where it could be expected to operate reliably for the additional 30 years expected from the plant. Clearly the objective is to suitably restore the equipment to serviceability without doing more refurbishment work than is warranted - without replacing equipment except where absolutely necessary. The first task in such a program is determination of its scope - i.e. a listing of all heat exchangers. That list included everything from the steam generators (which required replacement, now completed), to much smaller heat exchangers in the heavy water upgrader systems (which were found to be in very good overall condition). There is also a very large number of other so-called 'balance-of-plant' heat exchangers; these include the maintenance coolers, moderator heat exchangers, shutdown coolers and a whole raft of smaller coolers - many of which are cooled directly by lake water with its potential for bio-fouling and 'BIC' (Biologically Induced Corrosion). This paper focuses primarily on the engineering assessment, inspection, repair and general refurbishment of the balance-of-plant heat exchangers. As will be discussed in the paper, the assessment of the inspection results for those heat exchangers revealed a number of forms of degradation, much of it associated with secondary side fouling in lake water cooled vessels. These findings necessitated a variety of responses including recommendations for future inspection, tube plugging, secondary side chemical cleaning, shell replacement and complete vessel replacement. (author)

Availability note (English)

Available as a slide presentation also.
Part of:
Sixth CNS international steam generator conference on 'management of real-life equipment conditions and solutions for the future'

Additional details

Publishing Information

Publisher
Canadian Nuclear Society
Imprint Place
Toronto, Ontario (Canada)
ISBN
0-919784-96-8
Imprint Title
Sixth CNS international steam generator conference on 'management of real-life equipment conditions and solutions for the future'
Imprint Pagination
236 Megabytes
Journal Page Range
[17 p.]

Conference

Title
6. CNS international steam generator conference
Dates
8-11 Nov 2009
Place
Toronto, Ontario (Canada)

INIS

Country of Publication
Canada
Country of Input or Organization
Canada
INIS RN
46040993
Subject category
S21: SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS;
Resource subtype / Literary indicator
Conference, Non-conventional Literature
Descriptors DEI
BRUCE SITE; CANDU TYPE REACTORS; DECOMPOSITION; EVALUATION; REACTOR MAINTENANCE; STEAM GENERATORS; WATER CHEMISTRY
Descriptors DEC
BOILERS; CHEMICAL REACTIONS; CHEMISTRY; HEAVY WATER MODERATED REACTORS; MAINTENANCE; POWER REACTORS; PRESSURE TUBE REACTORS; REACTOR SITES; REACTORS; THERMAL REACTORS; VAPOR GENERATORS

Optional Information

Notes
Paper 1.04, 9 refs., 8 figs.