Summary of the engineering assessment of inactive uranium mill tailings, Green River site, Green River, Utah

Description

Radon gas released from the 123,000 tons of tailings at the Green River site constitutes the most significant environmental impact, although windblown tailings and external gamma radiation also are factors. The five alternative actions range from millsite decontamination with the addition of 3 m of stabilization cover material, to removal of the tailings to remote disposal sites and decontamination of the tailings site. Cost estimates for the five options range from about $4,300,000 for stabilization in-place, to about $9,600,000 for disposal at a distance of about 30 miles. Three principal alternatives for the reprocessing of the Green River tailings were examined: heap leaching, treatment at an existing mill, and reprocessing at a new conventional mill constructed for tailings reprocessing. The cost of the uranium recovered would be about $1,800/lb by heap leach and $1,600/lb by conventional plant processes

Availability note (English)

MF available from INIS under the Report Number; Available from NTIS., PC A04/MF A01.

Files

Restricted

The record is publicly accessible, but files are restricted to users with access.

Additional details

Publishing Information

Imprint Pagination
51 p.
Report number
DOE/UMT--0114S