Published November 1995
| Version v1
Journal article
Probabilistic analysis of limiting conditions for operation action requirements including risk of shutdown
Creators
- 1. Avaplan Oy, Espoo (Finland)
- 2. Brookhaven National Lab., Upton, NY (United States). Department of Advanced Technology
Description
When the systems needed to shut down a nuclear power plant are inoperable or degraded, the risk of shutting down the plant may be comparable to, or even higher than, that of continuing power operation with the equipment inoperable but giving priority to repairs. This concern arises because the plant may have insufficient capability for removing decay heat during the shutdown. However, in many cases, plant technical specifications require immediate shutdown of the plant. Risk-based analyses for various alternatives of operational policy available in such situations are examined. These analyses can be used to define the risk-effective requirements for those standby safety systems
Additional details
Publishing Information
- Journal Title
- Nuclear Technology
- Journal Volume
- 112
- Journal Issue
- 2
- Journal Page Range
- p. 250-265.
- ISSN
- 0029-5450
- CODEN
- NUTYBB
INIS
- Country of Publication
- United States
- Country of Input or Organization
- United States
- INIS RN
- 27022707
- Subject category
- S22: GENERAL STUDIES OF NUCLEAR REACTORS;
- Descriptors DEI
- AFTER-HEAT REMOVAL; ENGINEERED SAFETY SYSTEMS; FAILURES; NUCLEAR POWER PLANTS; REACTOR OPERATION; REACTOR SAFETY; REACTOR SHUTDOWN; RISK ASSESSMENT; SAFETY ANALYSIS; SPECIFICATIONS
- Descriptors DEC
- NUCLEAR FACILITIES; OPERATION; POWER PLANTS; REMOVAL; SAFETY; SHUTDOWN; THERMAL POWER PLANTS