Published 1987 | Version v1
Book

Preparation for commissioning of nuclear plant with reference to British Nuclear Fuels Plc fuel handling plant project

Creators

  • 1. British Nuclear Fuels Ltd., Risley (UK)

Description

The new Fuel Handing Plant at British Nuclear Fuels Sellafield is part of a Pound 550M complex which provides facilities for the receipt, storage and mechanical preparation of both magnox and A.G.R. fuel. The plant is very large and complex with considerable use of computer based process control systems, providing for physical and nuclear safety. The preparation of such plant for ''active'' commissioning necessitates a great many physical checks and technical evaluations in support of its safety case. This paper describes arrangements for plant commissioning checks, against the regulatory framework and explains the physical preparations necessary for their timely accomplishment. (author)

Additional details

Publishing Information

Publisher
Institution of Mechanical Engineers.
Imprint Place
London (UK)
Imprint Title
The safe handling of spent nuclear fuel at Sellafield
Imprint Pagination
67 p.
Journal Page Range
p. 61-68.

Conference

Title
Seminar on the safe handling of spent nuclear fuel at Sellafield.
Dates
19 Feb 1987.
Place
London (UK).

INIS

Country of Publication
United Kingdom
Country of Input or Organization
United Kingdom
INIS RN
20060639
Subject category
S42: ENGINEERING; S11: NUCLEAR FUEL CYCLE AND FUEL MATERIALS;
Resource subtype / Literary indicator
Conference
Descriptors DEI
LICENSING PROCEDURES; PERFORMANCE TESTING; QUALITY ASSURANCE; SAFEGUARD REGULATIONS; SELLAFIELD REPROCESSING PLANT
Descriptors DEC
ADMINISTRATIVE PROCEDURES; FUEL REPROCESSING PLANTS; LAW; NUCLEAR FACILITIES; REGULATIONS; TESTING