Shippingport Atomic Power Station (PWR). Technical progress report, January 26, 1981-July 25, 1981

Description

The Shippingport Atomic Power Station was operated with the Light Water Breeder Reactor (LWBR) core primarily at high power levels (base load) until April 24, 1981, when a planned semiannual shutdown for testing and maintenance began. Station startup commended May 27, 1981. High power operation was achieved on June 4, 1981, and continued through the end of the report period, when the LWBR core had achieved 22,022 EFPH. Several brief reductions in power and the brief station shutdowns occurred during this period. Maxmum allowable thermal power continued to be 80% of 236.6 MW thermal with reactor coolant flow at 100%, coolant pressure at 1600 psig and average temperature at 5210F

Availability note (English)

MF available from INIS under the Report Number; Available from NTIS., PC A03/MF A01.

Files

Restricted

The record is publicly accessible, but files are restricted to users with access.

Additional details

Publishing Information

Imprint Pagination
43 p.
Report number
WAPD-MRP--156

INIS

Country of Publication
United States
Country of Input or Organization
United States
INIS RN
13665793
Subject category
S21: SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS;
Resource subtype / Literary indicator
Progress Report
Descriptors DEI
LWBR TYPE REACTORS; REACTOR MAINTENANCE; REACTOR OPERATION; REACTOR SHUTDOWN; SHIPPINGPORT REACTOR
Descriptors DEC
BREEDER REACTORS; ENRICHED URANIUM REACTORS; MAINTENANCE; OPERATION; POWER REACTORS; PWR TYPE REACTORS; REACTORS; THERMAL REACTORS; WATER COOLED REACTORS; WATER MODERATED REACTORS