Three steps to a more successful quality assurance program

Creators

  • 1. Bechtel Power Corp., Ann Arbor, Mich., (USA)

Description

The three steps that will be presented are by no means a cure-all for the variety of problems and challenges that a Quality Assurance (QA) Department is faced with in its role in the design and construction of a nuclear power plant. However, these steps are considered to be three of the most important ones in the realization of an effective and efficient QA program. Step 1. Awareness. With the multitude of people involved in activities that effect the resultant Quality of Design, Procurement, and Construction of a nuclear power plant, a concerted effort has been put forth at Bechtel to promote 'Quality Awareness'. This effort has resulted in presentations to thousands of engineers, buyers, superintendents, supervisors and many others to make them more aware of their role in the Quality program. These presentations cover the Quality criteria, organizations, manuals, and implementation responsibilities that constitute the Company Quality program. In addition to the above, many specialized courses covering inspection techniques, communications, auditing, problem solving, etc. have been given to the people involved in the Generic Quality Assurance functions. Step 2. Attitude. Nuclear Power Quality requirements are quite stringent and have presented additional requirements to engineers, buyers, and superintendents who have previously designed and constructed fossil fuel power plants. Logically there was a resistance to these new requirements and a number of attitudes had to be changed. The most effective way that we have found to accomplish this is through communications from top management expressing their support of the Quality Program. Step 3. Objective and economical compliance. With the increased awareness and a more positive attitude toward Quality requirements, Bechtel has been able to devote considerable effort on finding effective methods to comply with Quality requirements in the most economical way. The complete presentation will include several examples of the implementation of each of the above steps taken from actual experience. (author)

Additional details

Publishing Information

Publisher
IAEA.
Imprint Place
Vienna
ISBN
92-0-050075-7
Imprint Title
Reliability of nuclear power plants
Imprint Pagination
p. 633-636.
Series
Proceedings series.

Conference

Title
Symposium on the reliability of nuclear power plants.
Dates
14 Apr 1975.
Place
Innsbruck, Austria.

INIS

Country of Publication
International Atomic Energy Agency (IAEA)
Country of Input or Organization
International Atomic Energy Agency (IAEA)
INIS RN
7233916
Subject category
S21: SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS;
Resource subtype / Literary indicator
Conference
Descriptors DEI
CONSTRUCTION; ECONOMICS; NUCLEAR POWER PLANTS; QUALITY ASSURANCE; REACTOR OPERATION
Descriptors DEC
NUCLEAR FACILITIES; OPERATION; POWER PLANTS; THERMAL POWER PLANTS

Optional Information

Secondary number(s)
IAEA-SM--195/41.