Heat balance calculation and feasibility analysis for initial startup of Fuqing nuclear turbine unit with non-nuclear steam
Description
Non-nuclear steam run up compared with nuclear steam run up, can verify the design, manufacture, installation quality of the unit, at the same time shorten the follow-up duration of the entire group ready to start debugging time. In this paper, starting from the first law of thermodynamics, Analyzed Heat balance Calculation and Feasibility analysis for Initial startup of Fuqing nuclear Turbine unit with Non-nuclear steam, By the above calculation, to the system requirements and device status on the basis of technical specifications, confirmed the feasibility of Non-nuclear steam running up in theory. After the implementation of the Non-nuclear turn of Fuqing unit, confirmed the results fit with the actual process. In summary, the Initial startup of Fuqing turbine unit with Non-nuclear steam is feasible. (authors)
Additional details
Publishing Information
- Journal Title
- China Nuclear Power
- Journal Volume
- 7
- Journal Issue
- Suppl.2
- Journal Page Range
- p. 103-108
- ISSN
- 1674-1617
INIS
- Country of Publication
- China
- Country of Input or Organization
- China
- INIS RN
- 48083260
- Subject category
- S21: SPECIFIC NUCLEAR REACTORS AND ASSOCIATED PLANTS;
- Descriptors DEI
- COMPARATIVE EVALUATIONS; DESIGN; FUQING-1 REACTOR; HEAT; IMPLEMENTATION; INSTALLATION; NUCLEAR POWER PLANTS; SPECIFICATIONS; START-UP; STEAM; STEAM TURBINES; THERMODYNAMICS
- Descriptors DEC
- ENERGY; ENRICHED URANIUM REACTORS; EQUIPMENT; EVALUATION; MACHINERY; NUCLEAR FACILITIES; POWER PLANTS; POWER REACTORS; PWR TYPE REACTORS; REACTORS; THERMAL POWER PLANTS; THERMAL REACTORS; TURBINES; TURBOMACHINERY; WATER COOLED REACTORS; WATER MODERATED REACTORS
Optional Information
- Notes
- 2 figs., 7 tabs., 2 refs.