Published March 1985 | Version v1
Journal article

District heat for eight communities from the Beznau heat and power plant

  • 1. Refuna A.G., Baden (Switzerland). Technische Projektleitung
  • 2. Nordostschweizerische Kraftwerke A.G., Baden

Description

Almost one year after the first heat supply from the Beznau cogeneration plant of the North East Swiss Power Consortium on 15. November 1983 and the initial heat supply to the Swiss Institute for Reactor Research and the Swiss Institute for Nuclear Research, the heat supply programme of Refuna now has a totally new component: since the start of the 1984/85 heating period 100 provate consumers (small consumers and large industrial customers) in neighbouring communities are also obtaining heat from the Beznau plant. Additional premises are being linked up daily and 15 km of Refuna's new district heating network are now in service. (orig.)

Abstract (German)

Knapp ein Jahr nach der Inbetriebnahme der ersten Waermeauskopplung im Kernkraftwerk Beznau der Nordostschweizerischen Kraftwerke (NOK) am 15. November 1983 und der erstmaligen Waermeabgabe an das Eidgenoessische Institut fuer Reaktorforschung (EIR) und das Schweizerische Institut fuer Nuklearforschung (SIN) hat die Waermelieferung durch die Refuna eine neue Komponente erhalten: Seit dem Beginn der Heizsaison 1984/85 werden bereits 100 private Waermeabnehmer (Kleinabnehmer und industrielle Grossverbraucher) in den angeschlossenen Gemeinden mit Waerme aus dem Kernkraftwerk Beznau versorgt. Taeglich werden weitere Liegenschaften angeschlossen. 15 km Hauptleitungen des neuerrichteten Fernwaermenetzes des Refuna sind in Betrieb. (orig.)

Additional details

Additional titles

Original title (German)
Fernwaerme fuer acht Gemeinden vom Kernkraftwerk Beznau

Publishing Information

Journal Title
Fernwaerme Int.
Journal Volume
14
Journal Issue
2
Series
CODEN: FRWMA.;Fernwaerme Int.
Journal Page Range
46-50
ISSN
0340-3572