Commissioning of the LCLS LINAC

Description

The Linac Coherent Light Source (LCLS) X-ray free electron laser project is currently under construction at the Stanford Linear Accelerator Center (SLAC). A new injector and upgrades to the existing accelerator were installed in two phases in 2006 and 2007. We report on the commissioning of the injector, the two new bunch compressors at 250MeV and 4.3 GeV, and transverse and longitudinal beam diagnostics up to the end of the existing linac at 13.6 GeV. The commissioning of the new transfer line from the end of the linac to the undulator is scheduled to start in November 2008 and for the undulator in March 2009 with first light to be expected in July 2009.

Availability note (English)

Available from http://www.slac.stanford.edu/cgi-wrap/getdoc/slac-pub-14118.pdf; http://www.slac.stanford.edu/cgi-wrap/pubpage?slac-pub-14118.html; PURL: https://www.osti.gov/servlets/purl/981666-iUUeJk/

Additional details

Publishing Information

Imprint Pagination
5 p.
Report number
SLAC-PUB--14118

Conference

Title
Linear Accelerator Conference 2008
Acronym
LINAC 08
Dates
29 Sep - 3 Oct 2008
Place
Victoria, BC (Canada)

INIS

Country of Publication
United States
Country of Input or Organization
United States
INIS RN
41091185
Subject category
S43: PARTICLE ACCELERATORS;
Resource subtype / Literary indicator
Conference, Non-conventional Literature
Descriptors DEI
ACCELERATORS; COMMISSIONING; COMPRESSORS; CONSTRUCTION; FREE ELECTRON LASERS; LIGHT SOURCES; LINEAR ACCELERATORS; STANFORD LINEAR ACCELERATOR CENTER; WIGGLER MAGNETS
Descriptors DEC
ACCELERATORS; EQUIPMENT; LASERS; MAGNETS; NATIONAL ORGANIZATIONS; RADIATION SOURCES; US DOE; US ERDA; US ORGANIZATIONS

Optional Information

Contract/Grant/Project number
AC02-76SF00515
Funding organization
US Department of Energy (United States)