Published August 1, 2019 | Version v1
Journal article

Integrating House of Risk Method with PESTLE and CIMOSA for Risk Assessment of Java-Bali I Power Plant Construction Project

  • 1. Department of Technology Management, Institut Teknologi Sepuluh Nopember, Surabaya (Indonesia)
  • 2. Department of Industrial Engineering, Institut Teknologi Sepuluh Nopember, Surabaya (Indonesia)

Description

Java-Bali I Combined Cycle Power Plant Project is part of 35,000 MW electrical generating development program. To fulfil the project construction objectives, a risk assessment is needed. It is started with risk identification using PESTLE analysis and CIMOSA approach. It can be identified that there are 18 risk events for external factor, 22 risk events for internal factor and 54 risk agents that will be analysed using House of Risk (HOR) stage 1 method. Focus Group Discussion (FGD) is held for assessing severity of each risk events and occurrence of risk agents, also the correlation between them. Using HOR stage 1 is obtained Aggregate Risk Potential (ARP) value for each risk agents. Using pareto analysis, 11 risk agents is chosen as priority and will be evaluated using HOR stage 2. Using HOR stage 2 method, 7 preventive actions (PA) are identified to prevent risk agents occur. As final result, using Cost Benefit Analysis (CBA), 7 recommendations is suggested in order to make project successful according to the target specified. (paper)

Availability note (English)

Available from http://dx.doi.org/10.1088/1757-899X/598/1/012044

Additional details

Publishing Information

Journal Title
IOP Conference Series. Materials Science and Engineering (Online)
Journal Volume
598
Journal Issue
1
Journal Page Range
[8 p.]
ISSN
1757-899X

Conference

Title
Annual Conference on Industrial and System Engineering (ACISE) 2019
Dates
23-24 Apr 2019
Place
Semarang (Indonesia)

INIS

Country of Publication
United Kingdom
Country of Input or Organization
International Atomic Energy Agency (IAEA)
INIS RN
53003259
Subject category
S42: ENGINEERING;
Resource subtype / Literary indicator
Conference
Descriptors DEI
COMBINED-CYCLE POWER PLANTS; CONSTRUCTION; COST BENEFIT ANALYSIS; RECOMMENDATIONS; RISK ASSESSMENT
Descriptors DEC
ECONOMIC ANALYSIS; ECONOMICS; POWER PLANTS; THERMAL POWER PLANTS