Determination of magnet realignment period based on smoothing analysis
Creators
- 1. Pohang Inst. of Science and Technology, Pohang Accelerator Lab., Pohang (Korea, Republic of)
Description
A deformation measurement of the PLS storage ring tunnel shows that the settlement of the tunnel floor keeps going on about 3 mm (peak-to-valley) a year, and the lateral deformation is within the range of ±1 mm. The tunnel settlement of 3 mm results in the storage ring deformation of ±1.5 mm a year in vertical direction. Results of the case studies for the estimation of relative positional errors by a smoothing analysis from 1995 to 1997 are summarized as follows: a low filter method for the smoothing analysis was successfully employed, and the storage ring magnets are placed within 2σ (±0.3 mm) range from the smoothed curve. While the relative positional errors are well within the tolerance of 0.15 mm, the absolute positional tolerance that is the range of maximum deviations of magnets from the ideal beam path is extended to ±3 mm, which is derived from the experience of storage ring operation. Therefore, we estimate the period of magnet realignment of the PLS storage ring should be about 2 years. (author)
Additional details
Identifiers
- URL
- http://www.kek.jp;
Publishing Information
- Imprint Title
- Proceedings of the first Asian particle accelerator conference (APAC98)
- Imprint Pagination
- 960 p.
- Journal Page Range
- p. 286-288
- Report number
- KEK-PROC--98-10
Conference
- Title
- 1. Asian particle accelerator conference
- Acronym
- APAC98
- Dates
- 23-27 Mar 1998
- Place
- Tsukuba, Ibaraki (Japan)
INIS
- Country of Publication
- Japan
- Country of Input or Organization
- Japan
- INIS RN
- 31007220
- Subject category
- S43: PARTICLE ACCELERATORS;
- Resource subtype / Literary indicator
- Conference, Non-conventional Literature
- Descriptors DEI
- ALIGNMENT; DEFORMATION; MAGNETS; POSITIONING; STORAGE RINGS; SYNCHROTRON RADIATION SOURCES; TUNNELS
- Descriptors DEC
- EQUIPMENT; RADIATION SOURCES; UNDERGROUND FACILITIES