Published September 2012 | Version v1
Journal article

Methodology for predicting flow-accelerated corrosion wear using unreferenced multiple inspection data

  • 1. Department of Civil and Environmental Engineering, University of Waterloo, 200 University Avenue West, Waterloo, Ontario N2L 3G1 (Canada)

Description

Highlights: ► We develop a new method for flow accelerated corrosion (FAC) wear prediction. ► The method is based on a small circular patch near the point of minimum thickness. ► Inspection uncertainties and errors are minimized by surface interpolation. ► The method is applied to the assessment of feeder piping in CANDU reactors. ► The results provide valuable risk information for long-term planning and LCM. - Abstract: The lack of fixed spatial referencing in inspection data is a confounding factor in the assessment of wall thinning due to flow-accelerated corrosion (FAC). Because of the loss of wall thickness over time, it is impossible to match any two unreferenced points precisely between inspection outages, making the use of point-to-point comparison methods highly uncertain. In this study, we develop a new methodology for estimating the FAC rate and component lifetime from spatially unreferenced inspection data. The method is based on a small circular patch that represents the minimum wall thickness as a random variable. This allows the predictions to be performed in a probabilistic setting, hence providing valuable risk information for long-term replacement planning and life-cycle management. The uncertainty and errors introduced by inspection and grid coverage are minimized in the analysis by fitting a continuous surface through the inspection data using the method of kriging. The developed methodology is applied to the assessment of carbon steel feeder piping in CANDU reactors, where the economic and safety consequences of FAC can be highly significant. Based on the analysis of a large industry dataset, FAC in feeder piping appears to be a relatively uniform and stationary process. The results of the study demonstrate the key advantages of the developed methodology and how it can be used to support risk-informed decision making with respect to FAC at power plants.

Availability note (English)

Available from http://dx.doi.org/10.1016/j.nucengdes.2012.06.003

Additional details

Identifiers

DOI
10.1016/j.nucengdes.2012.06.003;
PII
S0029-5493(12)00321-4;

Publishing Information

Journal Title
Nuclear Engineering and Design
Journal Volume
250
Journal Page Range
p. 317-325
ISSN
0029-5493
CODEN
NEDEAU

Optional Information

Copyright
Copyright (c) 2012 Elsevier Science B.V., Amsterdam, The Netherlands, All rights reserved.