The work toward decommissioning of unit 1 through 4 of Fukushima Daiichi Nuclear Power Station of Tokyo Electric Power Company Incorporated

Creators

  • 1. Tokyo Electric Power Co., Inc., Tokyo (Japan)

Description

Since accident at Fukushima Daiichi nuclear power station (NPS), TEPCO had made strenuous efforts to settle the accident under the cooperation of the government and others concerned. At present, various works towards decommissioning had been done according to the revised mid-and-long-term roadmap decided by 'Council for the Decommissioning of TEPCO's Fukushima Daiichi NPS' on June 27, 2013. This article described present state and future perspective of decommissioning works based on mid-and-long-term action plan. 'Cold shutdown condition' was maintained at Units 1-3. The RPV bottom temperature and the PCV gaseous phase temperatures at Units 1-3 were ∼30-50degC (as of August), and maximum total release rate of radioactive materials was ∼0.01 billion Bq/h and radiation exposure dose at site boundaries was 0.03 mSv/year. Highly radioactive water accumulated in the building basement had been treated to be used for reactor cooling and contaminated water generated in this process was treated and stored. Several countermeasures against accumulated water increased by groundwater intrusion were prepared so as to mitigate sea water contamination and reduce the impact of radiation on the area outside the power station. According to revised mid-to-long-term roadmap towards the decommissioning of Units 1-4, current activities were: (1) preparation for fuel removal from the spent fuel pool and (2) R and D for fuel debris removal and radioactive waste processing and disposal. R and D consortium International Research Institute for Nuclear Decommissioning (IRID) was founded on August for R and D for nuclear decommissioning, advancing international/domestic alliance for decommissioning and human resource development for nuclear R and D. (T. Tanaka)

Availability note (English)

Available from DOI: https://doi.org/10.3327/jaesjb.55.11_639

Abstract (Japanese)

福島第一原子力発電所の事故以降,政府等関係者の協力のもと,事故の収束に全力を挙げて取り組んできた。現在は,2013年6月27日に「東京電力福島第一原子力発電所廃炉対策推進会議」で決定された改訂版中長期ロードマップに基づき廃止措置等に向けた取り組みを進めている。本稿では,現状と改訂版中長期ロードマップに基づく今後の見通しについて紹介する。(日本)

Additional details

Additional titles

Original title (Japanese)
東京電力福島第一原子力発電所1~4号機の廃止措置等に向けた取り組み

Identifiers

Publishing Information

Journal Title
Nippon Genshiryoku Gakkai-Shi
Journal Volume
55
Journal Issue
11
Journal Page Range
p. 639-643
ISSN
0004-7120

Optional Information

Notes
3 refs., 5 figs., 1 tab.; This record replaces 45016558; This record replaces 48048206