Project management with regulatory constraints: Return to service of San Onofre Unit 1

Creators

  • 1. Bechtel Power Corp.

Description

Station acceptance of the RTS work was completed in early November, 1984. The unit completed a successful integrated leak rate test, hot function test, and 200 hour warranty run in December, 1984 six weeks ahead of the CPUC mandate. Capital expenditures, although greater than the initial forecast, were two million dollars less than the 37.5 million dollar CPUC cap. The unit has run essentially trouble-free at current rated power until the current 1985 outage. Strategies and lessons learned that contributed to a successful RTS (e.g., all regulatory and economic constraints were met) included the use of numerous brainstorm sessions between SCE, Bechtel, and other consultants; innovative state of the art technical criterion (e.g., realistic versus overly conservative engineering); and budget and schedule contingencies consistent with the known and unknown risks

Additional details

Publishing Information

Journal Title
Proc. Am. Power Conf.
Journal Volume
48
Series
Proc. Am. Power Conf.
Journal Page Range
968-970
ISSN
0097-2126
CODEN
PAPWA

Conference

Title
American power conference.
Dates
14-16 Apr 1986.
Place
Chicago, IL (USA).

Optional Information

Secondary number(s)
CONF-860422--.