Recent solenoid-operated valve experiences involving maintenance and testing deficiencies

  • 1. Nuclear Regulatory Commission, Washington, DC (United States)

Description

The paper presents recent solenoid operated valve operating experience. It describes common-mode failures at the Salem Unit 2 and Peach Bottom Units 2 and 3 plants. At the Salem plant, a catastrophic failure of turbine equipment resulted in an outage of about 6 months. The Peach Bottom event involved repetitive failures of safety systems with a shorter outage. The lessons learned from both events are that prudent preventive maintenance and surveillance testing are needed to enhance safe economic plant operation

Additional details

Publishing Information

Imprint Title
Proceedings of the second NRC/ASME symposium on pump and valve testing
Imprint Pagination
598 p.
Journal Page Range
p. 199-205.
Report number
NUREG/CP--0123

Conference

Title
2. Nuclear Regulatory Commission (NRC)/American Society of Mechanical Engineers (ASME) symposium on pump and valve testing.
Dates
21-23 Jul 1992.
Place
Washington, DC (United States).

Optional Information

Secondary number(s)
EGG--2676; CONF-920732--.