Fast generation shedding equipment based on the observation of swings of generators
Creators
- 1. Tokyo Electric Power Co., Tokyo (Japan)
Description
This paper presents a new method and newly developed stabilizing equipment to prevent the loss of synchronism of generators in pumped-storage plants from spreading. The proposed method includes functions to estimate the swing of each generator by using on-line generator output sampled at a rate of 600 times per second after an occurrence of disturbance such as fault, faulty equipment and so on, to predict generator swing 200-300 milliseconds ahead and loss of synchronism between generators in pumped-storage plants and those in thermal and nuclear plants, and to decide the number of generators that must be shed to maintain stability. Tokyo Electric Power Co. (TEPCO) installed the newly developed stabilizing equipment based on this method in the power system in June, 1986
Additional details
Publishing Information
- Journal Title
- IEEE Transactions on Power Systems
- Journal Volume
- 3
- Journal Issue
- 2
- Series
- IEEE Trans. Power Syst.
- Journal Page Range
- 439-446
- ISSN
- 0885-8950
- CODEN
- ITPSE
INIS
- Country of Publication
- United States
- Country of Input or Organization
- United States
- INIS RN
- 20049393
- Subject category
- S22: GENERAL STUDIES OF NUCLEAR REACTORS;
- Descriptors DEI
- DISTURBANCES; ELECTRIC GENERATORS; EQUIPMENT PROTECTION DEVICES; HYDROELECTRIC POWER PLANTS; JAPAN; NUCLEAR POWER PLANTS; ON-LINE CONTROL SYSTEMS; ON-LINE SYSTEMS; OPERATION; STABILITY; SYNCHRONIZATION; THERMAL POWER PLANTS
- Descriptors DEC
- ASIA; CONTROL SYSTEMS; DEVELOPED COUNTRIES; ELECTRICAL EQUIPMENT; EQUIPMENT; NUCLEAR FACILITIES; POWER PLANTS