Operating results obtained in a nuclear power plant with a sensor surveillance prototype

  • 1. EDF/DER, Chatou (France)
  • 2. CEN/Saclay (France)
  • 3. FRAMATOME, Paris-la-Defense (France)
  • 4. Westinghouse, Pittsburg (USA)

Description

Surveillance methods have been validated and specific equipment have been built to measure the response time of sensors from a nuclear power plant protection channel. The reason of the choice of this parameter is twofold: the sensor response time is representative of the sensor physical status and is also part of the overall channel response time. Two surveillance methods are used: noise analysis (by AR or PSD modeling), and loop current step response (for resistance thermometer detectors only). The methods were validated on test facilities and on nuclear power plants. Two test equipments were built and tested on plants. Results are represented and conclusions are drawn on the feasibility of such methods for sensor surveillance

Availability note (English)

MF available from INIS under the Report Number.

Abstract (French)

Des methodes de surveillance ont ete validees et un equipement specialise a ete realise pour mesurer en ligne le temps de reponse de capteurs appartenant a une chaine de protection de reacteur nucleaire. La raison du choix de ce parametre est double: le temps de reponse du capteur est representatif de l'etat physique du capteur et contribue au temps de response global de la chaine de protection, dont la verification periodique est a faire. Deux methodes de surveillance sont utilisees: l'analyse de bruit (part modele autoregressif ou par lissage de fonction de transfert) et le test de boucle de courant (pour les capteurs a resistance thermometrique seulement). Les methodes ont ete validees sur des boucles d'essais et sur des centrales nucleaires. Deux equipements de test on ete construits et testes en centrale. Les resultats obtenus sont presentes. Des conclusions sont tirees sur la possibilite d'utiliser de telles methodes pour la surveillance en ligne des capteurs

Files

15003019.pdf

Files (451.6 kB)

Name Size Download all
md5:d835c801448dc69a429c31dafd387b11
451.6 kB Preview Download

Additional details

Publishing Information

Imprint Pagination
19 p.
Report number
CEA-CONF--6717

Conference

Title
5. Symposium on power plant dynamics, control and testing.
Dates
21-23 Mar 1983.