D0 Central Tracking Solenoid Energization, Controls, Interlocks and Quench Protection Initial Validation Procedures

Description

This note presents the inspection and tests to be performed on the DZERO solenoid energization, controls, interlocks and quench protection system before it is energized for the first time. This test is to be performed with a 5000A jumper at the end of the bus instead of the solenoid. This system is based in DZERO room 511. A copy of this note shall be annotated, signed and dated by the person coordinating the procedure; and filed with the system maintenance records. Annotations shall include comments about any aspect of the procedure that is abnormal or unsuccessful. The following inspections and tests shall be performed by persons knowledgeable about the system. Each individual test step should be reviewed and understood before proceeding with that step.

Availability note (English)

Available from http://lss.fnal.gov/cgi-bin/find_paper.pl?d0-en-525.pdf.pdf; PURL: https://www.osti.gov/servlets/purl/1032085/

Additional details

Publishing Information

Imprint Pagination
31 p.
Report number
FERMILAB-D--0-EN-525

INIS

Country of Publication
United States
Country of Input or Organization
United States
INIS RN
43017726
Subject category
S43: PARTICLE ACCELERATORS;
Resource subtype / Literary indicator
Non-conventional Literature
Descriptors DEI
CONTROL SYSTEMS; FERMILAB TEVATRON; INSPECTION; INTERLOCKS; MAINTENANCE; PARTICLE TRACKS; QUENCHING; SOLENOIDS; SPECIFICATIONS; TESTING; VALIDATION
Descriptors DEC
ACCELERATORS; CYCLIC ACCELERATORS; ELECTRIC COILS; ELECTRICAL EQUIPMENT; EQUIPMENT; SYNCHROTRONS; TESTING

Optional Information

Contract/Grant/Project number
AC02-07CH11359
Notes
doi 10.2172/1032085
Funding organization
DOE Office of Science (United States)