Successful integration of the CERCLA and NEPA compliance processes in the Weldon Spring Site Remedial Action Project: A case study

Creators

Description

Special problems are posed for Department of Energy projects by the need to satisfy the environmental compliance documentation requirements of both the National Environmental Policy Act (NEPA) and the Comprehensive Environmental Response, Compensation and Liability Act (CERCLA). For the Weldon Spring Site Remedial Action Project, a two-part process was employed for the production of CERCLA documents that would also satisfy NEPA. One partinvolved determination of the proper level of documentation and integrating the information requirements of both Acts. The second part involved managing the Headquarters review, approval and issuance activities. The first full application of this process was completed during 1990 for two interrelated actions; removal of the bulk waste from the Weldon Spring Quarry (an Operable Unit requiring a Remedial Investigation/Feasibility Study), and construction of a water treatment plant for the Weldon Spring Chemical Plant (a non-time-critical removal requiring an Engineering Evaluation/Cost Analysis)

Part of:
Environmental remediation 1991: ''Cleaning up the environment for the 21st Century''

Additional details

Publishing Information

Imprint Title
Environmental remediation 1991: ''Cleaning up the environment for the 21st Century''
Imprint Pagination
896 p.
Journal Page Range
p. 615-619.
Report number
CONF-910981--

Conference

Title
Environmental remediation '91 conference.
Dates
8-11 Sep 1991.
Place
Pasco, WA (United States).