Published April 12, 1995
| Version v1
Report
Restricted
241-SY-101 Pump Decon System Acceptance Test Procedure
Description
The SY-101 Pump Decon System has components that consist of the water filter skid to assembly operation, the pump pit flooding system, and the system set up using air blow the water out of the decon hose. The Acceptance Test Procedure (ATP) consists of four parts. The first part will calibrate water and flow meters. The second part will determine the pressure loss on the water traveling through the filter skid at various flow rates. The third part will determine the length of time it takes to drain 1350 gallons of water out of a tank through 300 feet of discharge hose. The fourth part will verify that the calculated air volume and pressure in an air receiver is adequate to blow all the water out of a 2 inch diameter water hose
Availability note (English)
MF available from INIS under the Report Number; Also available from OSTI as DE95010574; NTIS; US Govt. Printing Office Dep.
Files
Additional details
Publishing Information
- Imprint Pagination
- 49 p.
- Report number
- WHC-SD--WM-ATP-125
INIS
- Country of Publication
- United States
- Country of Input or Organization
- United States
- INIS RN
- 26069992
- Subject category
- S22: GENERAL STUDIES OF NUCLEAR REACTORS; S61: RADIATION PROTECTION AND DOSIMETRY;
- Descriptors DEI
- CALIBRATION; CERTIFICATION; DECONTAMINATION; FILTERS; FLOW RATE; PRESSURE DROP; PUMPS; QUALITY ASSURANCE; RADIATION PROTECTION; TESTING
- Descriptors DEC
- CLEANING; EQUIPMENT
Optional Information
- Contract/Grant/Project number
- Contract AC06-87RL10930
- Funding organization
- USDOE, Washington, DC (United States).