Water-hammer experiences in the startup and early operation of the Shearon Harris plant

Creators

Description

During the startup testing and initial operation of any power plant, systems undergo planned transients to confirm their ability to respond as designed. In addition to planned testing, unplanned transients infrequently occur as equipment is initially used. Some of both the planned and unplanned transients result in water-hammer events. Several water-hammer events experienced during preoperational testing, power ascension testing, and early operation of the Shearon Harris nuclear power plant are presented. The cause, effect, and corrective actions undertaken to prevent recurrence for each event discussed are provided. In addition, examples of preventive measures taken, based on industry experience accrued at other plants, to prevent a similar occurrence at Shearon Harris are discussed

Additional details

Publishing Information

Journal Title
Transactions of the American Nuclear Society
Journal Volume
55
Series
Trans. Am. Nucl. Soc.
Journal Page Range
735
ISSN
0003-018X
CODEN
TANSA

Conference

Title
American Nuclear Society winter meeting.
Dates
15-19 Nov 1987.
Place
Los Angeles, CA (USA).

Optional Information

Secondary number(s)
CONF-8711195--.