Audit of dismantling charges for EDF's definitely stopped installations (EDF market C43K0C2740). Audit report on the robustness of dismantling charges for stopped EDF GEN1 installations (Chooz-A excluded) - Non technical summary

Description

After a general presentation of the technical audit (context and objective, process, date of audited documents, scope), and a presentation of report structure and of observation categories, this non-technical audit summary addresses the audit of dismantling scenarios (general analysis of dismantling scenarios, issue of dismantling works performed by remote operations, issue of final decontamination), proposes an analysis of EDF organisation regarding dismantling operations (adequacy between organisation and project performance, governance, tools to support project management, industrial strategy), addresses the way risks and uncertainties are taken into account, and discusses the relevance and robustness of costs and planning

Files

Restricted

The record is publicly accessible, but files are restricted to users with access.

Additional details

Additional titles

Original title (French)
Audit des charges de demantelement d'installations a l'arret definitif d'EDF (marche EDF C43K0C2740). Rapport d'audit sur la robustesse des charges de demantelements des installations EDF GEN1 a l'arret (hors Chooz-A) - Resume Non Technique

Publishing Information

Imprint Pagination
53 p.
Report number
INIS-FR--23-1160

Optional Information

Notes
Available from the INIS Liaison Officer for France, see the INIS website for current contact and E-mail addresses