Published January 4, 1984 | Version v1
Journal article

Dismantling of the first American nuclear power station of significant size

Creators

Description

The project assigned by the Department of Energy to General Electric for the complete dismantling of the 60MW pioneer Shippingport nuclear power station which was operational from 1957 to 1983 is described. The company sees one of its main aims as the gathering of practical experience for future decommissioning of worn-out nuclear power stations. New handling techniques for radioactive material are to be tried, and parts of the light-water reactor broken up under water. The work is expected to take four and a half years. (M.B.D.)

Additional details

Additional titles

Original title (German)
Abbruch des ersten groesseren US-Kernkraftwerkes

Publishing Information

Journal Title
Electro-Rev.
Journal Volume
76
Journal Issue
1
Series
Electro-Rev.
Journal Page Range
10
ISSN
0374-3101